Exam MB-335 topic 1 question 129 discussion

Actual exam question from Microsoft's MB-335
Question #: 129
Topic #: 1
[All MB-335 Questions]

A company uses Dynamics 365 Supply Chain Management for Process manufacturing.

You are reviewing the planned production orders for the next two weeks. There are several production orders for the same product. One order is scheduled to run the week after another order.

You need to optimize the planned production orders.

What should you do?

  • A. In Planned orders, combine the production orders.
  • B. Rerun master planning. Select the dynamic plan with a coverage time fence of two weeks.
  • C. Firm the orders.
  • D. Rerun master planning. Select the static plan with a coverage time fence of two weeks.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
CCexamn
4 days, 19 hours ago
Selected Answer: A
I would go with combining (grouping) the planned orders and your here and now issue is solved.
upvoted 1 times
...
Deetss
1 month, 3 weeks ago
Selected Answer: D
Looking again, I feel this should be "D." A dynamic plan will have real-time adjustments in which case re-running the dynamic plan does not make sense. As a result, "D" re-run the static plan seems to be the most correct.
upvoted 1 times
...
Deetss
2 months ago
Selected Answer: B
(B) Agree with BryanSCM, we want to use a dynamic plan in order to optimize planned production orders.
upvoted 1 times
...
BryanSCM
2 months, 1 week ago
The correct answer is B (rerun master planning with a dynamic plan) because it allows for real-time adjustments based on the latest data, optimizing the production orders scheduled closely together. A dynamic plan can adapt to changes, facilitating efficient use of resources and reducing potential downtime between orders. In contrast, D (rerun master planning with a static plan) generates a fixed net requirements plan that does not adjust until the next planning run, limiting responsiveness and optimization. Given the need for agility in process manufacturing, a dynamic plan is essential for efficiently managing overlapping production orders.
upvoted 1 times
...
kiio104
5 months, 2 weeks ago
Correct : https://learn.microsoft.com/en-us/dynamics365/supply-chain/master-planning/deprecated-master-plans#types-of-planning-methods
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago