You are a process engineer evaluating Lean vs. Discrete processing. You want to convert a Kanban item.
This item has the following Lean setup:
The setup uses a Lean schedule group with a throughput ratio = 2.
The process activity tied to production flow has the following runtime activity times: time = 3 min, per quantity = 1.
The work cell capacity has a model type of Throughput and an average throughput quantity of 60 per a capacity period of standard workday (8 hour day).
The throughput is 10 per hour.
You need to set up a Discrete operation to mirror the item’s production flow activity.
What should you do?

  • A. Create a route with a runtime = 6, a process quantity = 1, and the operation’s hours/time = 1.
  • B. Create a route with a runtime = 6, a process quantity = 1, and the operation’s hours/time = 0.0167 (e.g. 1 hour/60 minutes).
  • C. Create a route with a runtime = 1, a process quantity = 6, and the operation’s hours/time = 0.0167 (e.g. 1 hour/60 minutes).
  • D. Create a route with a runtime = 1, a process quantity = 1, and the operation’s hours/time = 0.0167 (e.g. 1 hour/60 minutes).
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
CCexamn
8 months, 2 weeks ago
Also similar to #138
upvoted 1 times
...
Deetss
9 months, 1 week ago
Selected Answer: B
I believe the answer is "B." Throughput ratio of 2 indicates product consumes two resources, in other words runtime 3min*2=6min for process quantity of 1. Since our runtime is in minutes, the operation hours/time must be 0.0167. https://learn.microsoft.com/en-us/training/modules/set-up-use-discrete-manufacturing-routes/create-operations-relations +throughput ratio link: https://learn.microsoft.com/en-us/dynamics365/supply-chain/production-control/tasks/define-lean-schedule-groups#associate-product
upvoted 1 times
...
juan1603
10 months, 1 week ago
Same Question than Question #86 of Topic 1 with other answer.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago