You are the lead consultant on a Dynamics 365 Field Service implementation for a commercial landscaping company.

Some jobs require landscape technicians to be scheduled on a job for multiple days.

What are three ways technicians can be scheduled over multiple days? Each correct answer presents a complete solution.

NOTE: Each correct selection is worth one point.

  • A. Manually on the schedule board.
  • B. Using Resource Scheduling Optimization (RSO).
  • C. Creating a resource group on the incident type.
  • D. Using the scheduling assistant.
  • E. Scheduling multiple resources to multiple days.
Show Suggested Answer Hide Answer
Suggested Answer: ADE 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
LnP
2 months ago
Selected Answer: ABD
I would say ABD. For multi-day jobs, you can configure RSO to schedule a technician for the entire duration of a work order by setting the effort required and time window. It ensures efficient allocation while respecting the technician’s availability across those days. About the option E. Scheduling multiple resources to multiple days This option is vague and not a distinct feature or method in Dynamics 365 Field Service. It could loosely describe an outcome of using the schedule board, RSO, or scheduling assistant, but it doesn’t represent a specific, standalone scheduling mechanism.
upvoted 1 times
...
hideouscrocodile
4 months, 3 weeks ago
Selected Answer: ADE
ADE are the right answers
upvoted 1 times
...
Vishakha_1420
11 months, 2 weeks ago
Selected Answer: ADE
https://learn.microsoft.com/en-us/dynamics365/field-service/schedule-multi-day-work
upvoted 2 times
MrEz
6 months ago
but "E. Scheduling multiple resources to multiple days. Most Voted" is not a "way" or a means.
upvoted 1 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago