Question #: 77
Topic #: 1
[All MB-335 Questions]

A company is implementing Dynamics 365 Supply Chain Management in their manufacturing environment. The manufacturing process uses formulas to direct material consumption on the batch orders.
During production some items in the formula must be consumed automatically from the production area, while some must be picked with their actual consumption reported on a pick list.
You need to determine which setup method is used for formula lines to allow for the desired mixed method picking processes.
What are two possible ways to achieve this goal? Each correct answer presents a complete solution,
NOTE: Each correct selection is worth one point.

  • A. Set the flushing principle on each formula line based on consumption method for the line.
  • B. Leave the flushing principle blank on formula lines and set default flushing principle on the items based on consumption method for the item.
  • C. Leave the flushing principle blank on formula lines and set resource consumption to direct flushing principle of materials based on consumption method for the line.
  • D. Leave the flushing principle blank on formula lines and set the default start value to Always for Automatic Bill of Material Consumption.
Show Suggested Answer Hide Answer
Suggested Answer: AB 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Mamaou
Highly Voted 1 year, 2 months ago
Selected Answer: AB
For me it's A and B, A it's the base of the flushing principle functionality. and and it's blank a the formula level, the system takes form the item. C can't be an answer for me because the resource consumption is used to determine where the raw materials it takes not how.
upvoted 7 times
...
griffin1212
Most Recent 6 months, 1 week ago
Selected Answer: AB
A and B are correct
upvoted 1 times
...
MFool
9 months, 4 weeks ago
I will go with A and B.
upvoted 2 times
...
LucasK69
1 year ago
Selected Answer: AD
Its A/D, The default flushing principle on the production BOM lines.
upvoted 1 times
...
GiSi1965
1 year, 2 months ago
Selected Answer: AB
The default flushing principle on the production BOM lines or batch order formula lines is taken from the product or the overridden value on the BOM or formulas.
upvoted 2 times
...
LOR_19
1 year, 3 months ago
Selected Answer: AC
A and C is correct. They asked for metod used for formula lines.
upvoted 1 times
...
Tonheidie
1 year, 3 months ago
Selected Answer: BC
The hierarchy starts at the released product, where the flushing principle has the value Start. On the bill of materials (BOM) or formula line, the flushing principle from the product can be overridden. The default flushing principle on the production BOM lines or batch order formula lines is taken from the product or the overridden value on the BOM or formulas. (So the answer A takes 'more time', therefor I think this B over A) https://learn.microsoft.com/en-us/dynamics365/supply-chain/production-control/flushing-principles
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago