DRAG DROP -
You are a Dynamics 365 for Field Service Dispatcher.
You need to use the schedule board to find resources for a work order. The work order can be completed by any resource who has the correct piece of equipment and who is available at 9:00 A.M during a selected week.
Which four steps must you take, in sequence, to successfully implement this capability within the schedule board? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.
Select and Place:

Show Suggested Answer Hide Answer
Suggested Answer:
References:
https://docs.microsoft.com/en-us/dynamics365/customer-engagement/field-service/multi-resource-scheduling-requirement-groups

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Adam_Stedry
8 months ago
In exam 08/23.
upvoted 2 times
...
Sravan8710
2 years, 9 months ago
Create a requirement group template Associate requirement group template to incident type Add incident type to WO Book the WO
upvoted 4 times
HassanSarhan
2 years, 4 months ago
correct
upvoted 1 times
...
...
fhqhfhqh
2 years, 11 months ago
This question was in the exam.
upvoted 3 times
...
Syedahamed
4 years, 3 months ago
The source given in answer section says, following the right sequence. 1. Create a requirement group template. 2. Create a new requirement group. 3. Book the requirement with the scheduling assistant. 4. Book the work order Not sure why the answer is marked differently here.
upvoted 2 times
evct
4 years, 3 months ago
If you read the section "Requirement groups for work orders"(https://docs.microsoft.com/en-us/dynamics365/field-service/multi-resource-scheduling-requirement-groups#requirement-groups-for-work-orders), you see there the correct order: 1-Create a requirement group template. 2-Associate an incident type to the requirement group template. 3-Add the incident type to a work order. 4-Book the work order. NOTE: Adding an incident type to a work order can also automatically add requirement groups.
upvoted 15 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago