Exam MB-330 topic 6 question 30 discussion

Actual exam question from Microsoft's MB-330
Question #: 30
Topic #: 6
[All MB-330 Questions]

A company uses Dynamics 365 Supply Chain Management. The company implements master planning.

The company reports delays in the supply chain that have resulted in late deliveries for products. You must simulate several broad delays across all products in the supply chain when calculating lead times. Daily planning for items must not be impacted.

You need to configure the system.

What should you configure?

  • A. Planned orders
  • B. Receipt margins
  • C. Master plans
  • D. Coverage groups
  • E. Released products
Show Suggested Answer Hide Answer
Suggested Answer: E 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Max2969
Highly Voted 1 year, 8 months ago
Maybe it is...Receipt margins? https://learn.microsoft.com/en-us/dynamics365/supply-chain/master-planning/planning-optimization/safety-margins
upvoted 7 times
Mamaou
1 year, 7 months ago
I agree, it's the purpose of the receipt margin.
upvoted 2 times
...
...
globeearth
Most Recent 2 days, 12 hours ago
Selected Answer: B
Receipt margins allow you to add buffer time to the expected receipt dates of supply (e.g., purchase orders or production orders) during master planning. This is useful for simulating delays in the supply chain, such as transportation or supplier delays, without altering the core daily planning logic. By adjusting the receipt margin, you can account for these broad delays across all products while keeping the daily planning process intact.
upvoted 1 times
...
IlseKH
4 months, 3 weeks ago
Selected Answer: D
answer from copilot..
upvoted 1 times
...
bromark10
1 year, 10 months ago
Should enable calculated delays on the master plan to apply for all? Don't really understand the answer given here..
upvoted 4 times
Deetss
1 year, 8 months ago
Master plans seems the most correct. You can have multiple master plans and can choose when to run and simulate "several broad delays across all products" plans. https://learn.microsoft.com/en-us/dynamics365/supply-chain/master-planning/master-plans#calculated-delays
upvoted 3 times
...
...
Vnes80
1 year, 11 months ago
I would answer Coverage group because you can set-up different margins
upvoted 4 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago