Exam CTFL-2018 topic 1 question 7 discussion

Actual exam question from ISTQB's CTFL-2018
Question #: 7
Topic #: 1
[All CTFL-2018 Questions]

Which of the following would achieve the HIGHEST level of testing independence for a project's system test level?

  • A. Training developers to design good tests for the test team to execute.
  • B. Outsourcing test design and execution to a different company.
  • C. Having the company's independent test team design and execute the tests.
  • D. Minimising contact between testers and developers during test design to avoid bias.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
kkk2022
Highly Voted 1 year, 2 months ago
Does anyone choose answer b instead of a?
upvoted 8 times
...
MouradO
Most Recent 3 weeks, 3 days ago
Le responsable du site : Merci de corriger , B est l'unique bonne reponse . Ma source : Syllabus 2018 page 67 extrait : "Les degrés d'indépendance dans les tests comprennent les niveaux suivants (allant d’un niveau d'indépendance faible à un niveau élevé) *Des testeurs indépendants externes à l'organisation, travaillant soit sur site (insourcing) soit hors site (outsourcing" C'est urgent de corriger svp .
upvoted 2 times
...
Abbasi279
1 month, 3 weeks ago
Hey, The corret answer is C. I dont know why most people are saying b Please see the following text from the official exam guide "System testing is typically carried out by independent testers who rely heavily on specifications. Defects in specifications (e.g., missing user stories, incorrectly stated business requirements, etc.) can lead to a lack of understanding of, or disagreements about, expected system behavior. Such situations can cause false positives and false negatives, which waste time and reduce defect detection effectiveness, respectively. Early involvement of testers in user story refinement or static testing activities, such as reviews, helps to reduce the incidence of such situations. "
upvoted 1 times
...
xrpuser
3 months, 3 weeks ago
This information is found on Page 62 of the syllabus. Given these options, the approach that would achieve the HIGHEST level of testing independence for a project's system test level would be: B. Outsourcing test design and execution to a different company.
upvoted 3 times
...
xrpuser
3 months, 3 weeks ago
B. Outsourcing test design and execution to a different company. This provides a completely separate entity that isn't influenced by internal development biases or pressures. This achieves a high level of independence.
upvoted 4 times
Courtman
1 month, 4 weeks ago
Answer A) is recorded as correct here, contradicting the syllabus - still, Answer B) is the most logical (without having read this or anything - the question is about "the HIGHEST level of independence" - that is of course when the system is tested by people who are otherwise not involved with the development.
upvoted 1 times
...
...
BRANNAS
3 months, 3 weeks ago
Selected Answer: B
B is correct
upvoted 2 times
...
Jay15
3 months, 4 weeks ago
A is correct
upvoted 1 times
...
SailuP
4 months, 1 week ago
C is correct
upvoted 1 times
...
AbhiMakam
4 months, 4 weeks ago
Answer is B
upvoted 2 times
...
OksanaRa
5 months, 2 weeks ago
There was not a single similar question on the exam
upvoted 1 times
...
JAS9898
6 months ago
Has someone recently appeared for this exam
upvoted 2 times
...
bhuppii
6 months, 1 week ago
B is correct
upvoted 2 times
...
skiw4o
7 months, 1 week ago
Would B be the correct answer to this question? Thet way the question is being asked is just so confusing. And it doesnt specify anywhere in the syllabus if for different test levels what the highest level of indendence would be. It only specifies in general what are from low to high the independence ....
upvoted 2 times
...
ktin15
7 months, 2 weeks ago
Selected Answer: C
A. WRONG. Developers can be bias with their work. B. WRONG. External tester may lack some important information about the project. C. CORRECT. Internal testers knows the project background and will not be bias. D. WRONG.
upvoted 2 times
...
andrebaptista
8 months, 4 weeks ago
Selected Answer: B
Correct answer is B. Level 5 (higest one) is using an external testing team
upvoted 2 times
...
knar
9 months, 2 weeks ago
The correct the answer is B.
upvoted 1 times
...
jedavilaq
10 months, 1 week ago
Respuesta correcta B
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago