Exam CTFL-AT topic 1 question 5 discussion

Actual exam question from ISTQB's CTFL-AT
Question #: 5
Topic #: 1
[All CTFL-AT Questions]

Iteration planning for Sprint 5 of your current project is complete. The plan for the sprint is to increase performance of the system, which of the following acceptance criteria would you expect for Sprint 5? i) User access for all roles has been validated. ii) A static analysis tool has been executed for all code. iii) 100% of the existing regression test suite has passed. iv) System is responding in less than 3 seconds, 90% of the time. v) A new version of internet Explorer has been included.

  • A. i, iii
  • B. iii, iv
  • C. iv, v
  • D. ii, v
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
meobeo90
3 weeks, 1 day ago
Selected Answer: C
This is a voting comment
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel