You work for company who are pioneers in smart energy technology. One of their core products is their home energy monitor that displays current and historic energy consumption data to many thousands of customers in their own homes. It has been designed to integrate with their other smart home products, including domestic lighting control systems via their HomeHub.
The company is planning to launch a new application for smartphones and tablets that will allow customers to view their energy readings remotely and also view their daily budget usage based on seasonal historic data. The application must support customers with disabilities.
The application is being delivered using a hybrid mix of agile and V-model methodologies over three iterations:
Iteration 1 - Development of the new application to work on the IOS operating system only.
Iteration 2 - Enhancement to the application to also work on the Android operating system.
Iteration 3 - Enhancement to the application to provide daily budget usage.
As the test analyst, you have been asked to review the risk register and design test conditions for the highest priority product risks that fall into your area of responsibility, relating to Iterations 1 and 2 only. Which of the following product risks would you design test conditions for first?