Question #: 4
Topic #: 1
[All CTFL v4.0 Questions]

In an Agile development model, the completion of testing or “done” is defined by which of the following?

  • A. Project management
  • B. Entry criteria
  • C. Exit criteria
  • D. The expected test completion date
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Edith200
3 months, 3 weeks ago
The correct answer is C
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...