Which of the following activities are done in release planning? i. Identifying testable user stories with acceptance criteria. ii. Elaborating the user stories into tasks. iii. Prioritizing the user stories. iv. Creating acceptance tests for the user stories. v. Analyzing risks for each of the user stories. vi. Performing high level estimation for the release.

  • A. Activities i, iv and vi
  • B. Activities ii and iv
  • C. Activities ii, iii and v
  • D. Activities i, iii and vi
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
53f03b1
5 months, 2 weeks ago
Selected Answer: A
iii is sprint planning act.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.