Which of the following describes the main purpose of a task management tool in agile projects?

  • A. A task management tool is used by team members to share ideas and collaborate on assigned tasks.
  • B. A task management tool is used to manage and track user stories, tests and other tasks.
  • C. A task management tool is used to store source code and automated tests.
  • D. A task management tool allows developers to continuously integrate their code.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
53f03b1
5 months, 3 weeks ago
Selected Answer: B
this is correct
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...