You are working on calculating the estimation for a project. You have been given the following numbers by your manager, who is considered to be an expert in estimation:
Optimistic = 35 days -
Likely = 40 days -
Pessimistic = 65 days -
Apply the three-point estimation technique, what is the proper expression of the final estimate?