You are working on calculating the estimation for a project. You have been given the following numbers by your manager, who is considered to be an expert in estimation:

Optimistic = 35 days -

Likely = 40 days -

Pessimistic = 65 days -
Apply the three-point estimation technique, what is the proper expression of the final estimate?

  • A. E is 46.3 days, SD = 35
  • B. E is 40 days, SD = 6.67
  • C. E is 37.3 days, SD = 43.3
  • D. E is 43.3 days, SD = 5
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Edith200
3 months, 3 weeks ago
D is correct: (35+(4*40)+65)/6=43.33 (65-35)/6=5
upvoted 1 times
...
matace
5 months, 3 weeks ago
Three-point estimate = [(O+4R+P)/6] In the formula, O represents the optimistic estimate, R represents the realistic estimate, and it receives a weight of 4. P is the pessimistic estimate.
upvoted 2 times
...
PAKO1333
5 months, 3 weeks ago
SD = L-O/6
upvoted 1 times
PAKO1333
5 months, 3 weeks ago
Sorry, it's correct . The formula is Pessimistic - Optimistic / 6
upvoted 1 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...