exam questions

Exam CT-TAE All Questions

View all questions & answers for the CT-TAE exam

Exam CT-TAE topic 1 question 36 discussion

Actual exam question from ISTQB's CT-TAE
Question #: 36
Topic #: 1
[All CT-TAE Questions]

You have investigated a new tool which enables the modelling of the SUT and can then generate test cases either manually or automatically. You have convinced your managers that the best way forward is to conduct a pilot project for this tool. You need to select a project to use for the pilot. You have the choice of the following projects:
Project A: A two-year project that is critical to the business and is currently in the requirement phase. This project is for a new e-commerce web site and is mostly being developed “in-house" although the payment system is being developed and delivered by a 3rd party provider.
Project B: A safety critical application for software to drive and park cars.
Project C: An upgrade to an important HR timesheet tracking application that will be available on a desktop and mobile application. This is a 1-month project developed in-house.
Project D The payment system from project A.
Which project would be BEST for the pilot?

  • A. Project A because it is a large project and has high visibility and is in the requirement phase.
  • B. Project B because it is a safety critical system and has high visibility.
  • C. Project C because it is a short, low priority project but is important
  • D. Project D because it is a small part of a larger project and will help show the tool’s capabilities.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
anitanik
7 months ago
The correct answer is C! A and B are wrong - as these are all critical projects and as noted in the syllabus - "Do not select a critical project. When the deployment of the TAS causes delay, this should not have major impact on critical projects.", page 45 of 84. In answer A is written that the payment system, suggested in answer D, is developed and delivered by a 3rd party provider. So, selecting this option for a pilot project will not have any added value. Answer C suggests short, low priority but important project. There's no saying it's trivial!
upvoted 3 times
...
rajlu717
7 months, 2 weeks ago
C looks to be correct answer.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam