exam questions

Exam CTAL-TM All Questions

View all questions & answers for the CTAL-TM exam

Exam CTAL-TM topic 6 question 26 discussion

Actual exam question from ISTQB's CTAL-TM
Question #: 26
Topic #: 6
[All CTAL-TM Questions]

In addition to risk, identify TWO other components of a testing strategy. 1 credit

  • A. The entry and exit criteria for each test phase
  • B. Test training needs for the project resources
  • C. The test design techniques to be used
  • D. Test performance indicators
  • E. The test schedule
Show Suggested Answer Hide Answer
Suggested Answer: AC 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Toprak
7 months, 1 week ago
Correct Answer is A and E
upvoted 1 times
...
radiostason
1 year ago
That is not the right answer. A - entry and exit criteria related to the Test Plan, according to the ISTQB Syllabus
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...