Exam CTFL-2018 topic 1 question 50 discussion

Actual exam question from ISTQB's CTFL-2018
Question #: 50
Topic #: 1
[All CTFL-2018 Questions]

Which one of the following would you typically expect to find in a test completion report for a test level?

  • A. Factors that are currently impeding test progress and the tests planned for the following day.
  • B. A summary of the testing performed and any deviations from the schedule, duration or effort of test activities.
  • C. The planned overall approach for testing and the resources required to perform the various test activities.
  • D. The proposed exit criteria and metrics reports for review and agreement by the stakeholders.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
AndrejCaky
Highly Voted 8 months, 1 week ago
I think it is B
upvoted 5 times
...
MouradO
Most Recent 3 weeks, 3 days ago
Responsable du site : Reponse B Merci de corriger SVP
upvoted 2 times
...
BRANNAS
3 months, 3 weeks ago
Selected Answer: B
B. A summary of the testing performed and any deviations from the schedule, duration, or effort of test activities. A test completion report for a test level typically includes a summary of the testing that was performed during that level, along with any deviations from the planned schedule, duration, or effort of test activities. This information provides an overview of the test activities that took place and highlights any discrepancies from the original plan.
upvoted 3 times
...
modoco
6 months, 3 weeks ago
Selected Answer: B
I think its B from syllabus https://astqb.org/assets/documents/CTFL-2018-Syllabus.pdf page 71 "When exit criteria are reached, the test manager issues the test summary report. This report provides a summary of the testing performed, based on the latest test progress report and any other relevant information. Typical test summary reports may include: • Summary of testing performed • Information on what occurred during a test period • Deviations from plan, including deviations in schedule, duration, or effort of test activities"
upvoted 4 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago