exam questions

Exam CAP All Questions

View all questions & answers for the CAP exam

Exam CAP topic 1 question 276 discussion

Actual exam question from ISC's CAP
Question #: 276
Topic #: 1
[All CAP Questions]

Your organization has named you the project manager of the JKN Project. This project has a BAC of $1,500,000 and it is expected to last 18 months.
Management has agreed that if the schedule baseline has a variance of more than five percent then you will need to crash the project. What happens when the project manager crashes a project?

  • A. Project costs will increase.
  • B. The amount of hours a resource can be used will diminish.
  • C. The project will take longer to complete, but risks will diminish.
  • D. Project risks will increase.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
fortune
4 months, 2 weeks ago
The answer should be A and D
upvoted 2 times
...
Joegley
2 years, 9 months ago
The answer to this question should be D.
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago