Question #: 53
Topic #: 1
[All CISSP-ISSMP Questions]

In which of the following SDLC phases is the system's security features configured and enabled, the system is tested and installed or fielded, and the system is authorized for processing?

  • A. Initiation Phase
  • B. Development/Acquisition Phase
  • C. Implementation Phase
  • D. Operation/Maintenance Phase
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
tld1486905
4 months, 2 weeks ago
Selected Answer: C
Implementation or Coding - The design is implemented in code, usually in several iterations. This phase involves front-end, middleware, and back-end development. It is the longest phase in the SDLC
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago