Which of the following contract types is described in the statement below? "This contract type provides no incentive for the contractor to control costs and hence is rarely utilized."
Cost plus a percentage of cost is a method of pricing contractors use when drafting contracts with clients when they cannot provide a final cost at the time of the contract.