exam questions

Exam CISSP-ISSMP All Questions

View all questions & answers for the CISSP-ISSMP exam

Exam CISSP-ISSMP topic 1 question 46 discussion

Actual exam question from ISC's CISSP-ISSMP
Question #: 46
Topic #: 1
[All CISSP-ISSMP Questions]

Which of the following contract types is described in the statement below? "This contract type provides no incentive for the contractor to control costs and hence is rarely utilized."

  • A. Cost Plus Fixed Fee
  • B. Cost Plus Percentage of Cost
  • C. Cost Plus Incentive Fee
  • D. Cost Plus Award Fee
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
tld1486905
4 months, 2 weeks ago
Selected Answer: B
Cost plus a percentage of cost is a method of pricing contractors use when drafting contracts with clients when they cannot provide a final cost at the time of the contract.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel