Question #: 40
Topic #: 1
[All CISSP-ISSMP Questions]

What component of the change management system is responsible for evaluating, testing, and documenting changes created to the project scope?

  • A. Scope Verification
  • B. Project Management Information System
  • C. Integrated Change Control
  • D. Configuration Management System
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
arawaco
3 months, 3 weeks ago
Scope verification: focus evaluating if project/product/service meets requirements of scope deliverables. Project management information system: project information is to organize/ collects and uses project information. Integrate change control: project modification requests. Configuration management syutem: Trackin, control canges and QA. Answer D
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...