Which of the following processes is described in the statement below? "It is the process of implementing risk response plans, tracking identified risks, monitoring residual risk, identifying new risks, and evaluating risk process effectiveness throughout the project."

  • A. Monitor and Control Risks
  • B. Identify Risks
  • C. Perform Qualitative Risk Analysis
  • D. Perform Quantitative Risk Analysis
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
arawaco
3 months, 3 weeks ago
A-Process executing risk response plans, training, id risks, residual risks, evaluate risks. C,D-Way to quantify risks. Answer A
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...