Actual exam question from ISC's SSCP
Question #: 6
Topic #: 4
[All SSCP Questions]

Which of the following recovery plan test results would be most useful to management?

  • A. elapsed time to perform various activities.
  • B. list of successful and unsuccessful activities.
  • C. amount of work completed.
  • D. description of each activity.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️
After a test has been performed the most useful test results for manangement would be knowing what worked and what didn't so that they could correct the mistakes where needed.
The following answers are incorrect:
elapsed time to perform various activities. This is incorrect because it is not the best answer, these results are not as useful as list of successful and unsuccessful activities would be to managment. amount of work completed. This is incorrect because it is not the best answer, these results are not as useful as list of successful and unsuccessful activities would be to managment. description of each activity. This is incorrect because it is not the best answer, these results are not as useful as list of successful and unsuccessful activities would be to managment.

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
formazionehs
11 months, 3 weeks ago
Correct answer is B
upvoted 1 times
...
nanson
12 months ago
Selected Answer: A
The recovery plan test result that would be most useful to management is: A. Elapsed time to perform various activities. Management often prioritizes efficient recovery after a disruptive event. Knowing the elapsed time to perform various activities during the recovery plan test provides crucial insights into the plan's effectiveness and the organization's ability to restore operations within acceptable time frames. This information helps in assessing the plan's readiness and identifying areas for improvement to enhance the organization's resilience in the face of disruptions.
upvoted 2 times
swiggharo
10 months, 1 week ago
Higher ups are not interested in the technical details. The answer is B.
upvoted 1 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...