Which of the following plans is designed to protect critical business processes from natural or man-made failures or disasters and the resultant loss of capital due to the unavailability of normal business processes?
Suggested Answer:disruption. The logistical plan is called a business continuity plan. Answer: C is incorrect. The crisis communication plan can be broadly defined as the plan for the🗳️
The business continuity plan is designed to protect critical business processes from natural or man-made failures or disasters and the resultant loss of capital due to the unavailability of normal business processes. Business Continuity Planning (BCP) is the creation and validation of a practiced logistical plan for how an organization will recover and restore partially or completely interrupted critical (urgent) functions within a predetermined time after a disaster or extended exchange of information before, during, or after a crisis event. It is considered as a sub-specialty of the public relations profession that is designed to protect and defend an individual, company, or organization facing a public challenge to its reputation. The aim of crisis communication plan is to assist organizations to plan is a plan devised for a specific situation when things could go wrong. Contingency plans are often devised by governments or businesses who want to be prepared for anything that could happen. Contingency plans include specific strategies and actions to deal with specific variances to assumptions resulting in a particular problem, emergency, or state of affairs. They also include a monitoring process and "triggers" for initiating planned actions. They are required to help disaster recovery plan should contain data, hardware, and software that can be critical for a business. It should also include the plan for sudden loss such as hard disc crash. The business should use backup and data recovery utilities to limit the loss of data.
A Business Continuity Plan focuses on keeping a company's critical functions running during and after a disruption to normal business operations. The primary goal of a BCP is to minimize the impact of an interruption to operations by ensuring that essential business functions can continue through redundancy, resiliency & backup mechanisms in place. As part of this planning process, companies identify their most critical processes and resources, outline procedures for restoring them quickly after a disruption occurs, allocate personnel accordingly to handle emergencies roles.
On the other hand, Disaster Recovery Planning(DRP) focuses specifically on recovering IT infrastructure following significant disruptions like cyber-attacks or natural disasters etc., It details steps required for bringing systems back online including prioritizing which systems need attention first depending upon vulnerabilities\criticality-grading defined under policy framework i.e GRC etc , where database should be restored from backups or should it be built using incremental data captured at various restore-points backed up into cold storage-restore-path.
upvoted 1 times
...
...
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
74gjd_37
5 months, 2 weeks ago74gjd_37
5 months, 2 weeks ago74gjd_37
5 months, 2 weeks ago