Question #: 61
Topic #: 2
[All CSSLP Questions]

What project management plan is most likely to direct the quantitative risk analysis process for a project in a matrix environment?

  • A. Risk analysis plan
  • B. Staffing management plan
  • C. Risk management plan
  • D. Human resource management plan
Show Suggested Answer Hide Answer
Suggested Answer: of the organization. Answer: D is incorrect. The human resources management plan does define how risks will be analyzed. Answer: B is incorrect. The staffing 🗳️
The risk management plan defines how risks will be identified, analyzed, responded to, and then monitored and controlled regardless of the structure

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
74gjd_37
5 months, 2 weeks ago
Selected Answer: C
C. Risk Management Plan.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago