Exam CSSLP topic 2 question 39 discussion

Actual exam question from ISC's CSSLP
Question #: 39
Topic #: 2
[All CSSLP Questions]

Billy is the project manager of the HAR Project and is in month six of the project. The project is scheduled to last for 18 months. Management asks Billy how often the project team is participating in risk reassessment in this project. What should Billy tell management if he's following the best practices for risk management?

  • A. Project risk management happens at every milestone.
  • B. Project risk management has been concluded with the project planning.
  • C. Project risk management is scheduled for every month in the 18-month project.
  • D. At every status meeting the project team project risk management is an agenda item.
Show Suggested Answer Hide Answer
Suggested Answer: Risk management is an ongoing project activity. It should be an agenda item at every project status meeting. Answer: A is incorrect. Milestones are good times to 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
74gjd_37
5 months, 2 weeks ago
Selected Answer: D
Option D, "At every status meeting, the project team risk management is an agenda item," would be the most appropriate answer if Billy is following best practices for risk management. Regular and frequent reassessment of risks is indeed critical to identifying new or changing risks as soon as possible, which allows teams to mitigate those risks effectively before they become major issues that threaten to derail a project. Therefore, discussing risks at each status meeting ensures that all potential challenges are identified and addressed promptly throughout the entirety of the 18-month HAR Project.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago