Question #: 27
Topic #: 1
[All CISSP-ISSMP Questions]

Walter is the project manager of a large construction project. He'll be working with several vendors on the project. Vendors will be providing materials and labor for several parts of the project. Some of the works in the project are very dangerous so Walter has implemented safety requirements for all of the vendors and his own project team. Stakeholders for the project have added new requirements, which have caused new risks in the project. A vendor has identified a new risk that could affect the project if it comes into fruition. Walter agrees with the vendor and has updated the risk register and created potential risk responses to mitigate the risk. What should Walter also update in this scenario considering the risk event?

  • A. Project contractual relationship with the vendor
  • B. Project management plan
  • C. Project communications plan
  • D. Project scope statement
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
arawaco
3 months, 3 weeks ago
B- Project management plan contains: scope management, budget, progress, resources and more.
upvoted 1 times
...
Cyberbug2021
1 year, 3 months ago
these are pmp question not cissp-issmp questions
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted