exam questions

Exam CISM All Questions

View all questions & answers for the CISM exam

Exam CISM topic 1 question 763 discussion

Actual exam question from Isaca's CISM
Question #: 763
Topic #: 1
[All CISM Questions]

Which of the following is the MOST important criterion when deciding whether to accept residual risk?

  • A. Cost of replacing the asset
  • B. Annual loss expectancy (ALE)
  • C. Cost of additional mitigation
  • D. Annual rate of occurrence
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
[Removed]
Highly Voted 11 months, 2 weeks ago
Selected Answer: C
According to the Certified Information Security Manager (CISM) Review Manual: "Decisions to accept residual risk should be based on considerations such as the cost-effectiveness of additional mitigation, the criticality of the asset to the enterprise’s mission, the asset’s value and the impact of the asset’s loss." (CISM Review Manual 15th Edition, p. 124)
upvoted 6 times
...
Souvik124
Highly Voted 1 year, 4 months ago
The MOST important criterion when deciding whether to accept residual risk is the cost of additional mitigation. Therefore, the correct answer is option C.
upvoted 5 times
cangurer
1 year, 3 months ago
I think B is correct, in order to compare the cost you should know the ALE,
upvoted 6 times
...
...
1899f17
Most Recent 1 month, 2 weeks ago
B. Annual loss expectancy (ALE)
upvoted 1 times
...
Marcelus1714
5 months ago
Selected Answer: C
Cost of additional mitigation. What if you have a high ALE but the cost of mitigation is even higher. I believe is always how much it cost.
upvoted 1 times
...
AlexJacobson
5 months, 2 weeks ago
I'm torn between B and, but leaning more towards C. If additional mitigation is not cost effective and the risk is still deemed too high, then the only other choice would be risk avoidance. But if that isn't possible, the only thing a business can do is accept the residual risk. ALE is important for determining a a potential loss an asset would suffer due to a threat realization over a year. But you can reduce ALE up to a point after which it stops being cost effective.
upvoted 1 times
...
POWNED
5 months, 2 weeks ago
Selected Answer: B
Most important is the ALE. You cannot decide to accept the risk if you have not defined the ALE and matched it up to the cost of mitigation.
upvoted 2 times
...
Evedzy
6 months, 1 week ago
ANSWER C : The security manager would be most concerned with whether residual risk would be reduced by a greater amount than the cost of adding additional controls. The other choices, although relevant, would not be as important.
upvoted 1 times
...
Saisharan
9 months ago
Cost of Mitigating the Asset so answer would be C
upvoted 2 times
...
Bl1024
9 months, 2 weeks ago
Selected Answer: C
If additional mitigation is too costly and not cost effective enough, you can only accept the risk
upvoted 2 times
...
richck102
1 year ago
i vote .....A. Cost of replacing the asset
upvoted 1 times
...
wello
1 year ago
Selected Answer: B
even if the risk is equal or greater than the asset value, the annual rate of occurrence matters. so I think B
upvoted 4 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago