Exam CRISC topic 1 question 1236 discussion

Actual exam question from Isaca's CRISC
Question #: 1236
Topic #: 1
[All CRISC Questions]

Which of the following is the BEST key performance indicator (KPI) to measure how effectively risk management practices are embedded in the project management office (PMO)?

  • A. Reduction in audits involving external risk consultants
  • B. Percentage of projects with key risk accepted by the project steering committee
  • C. Percentage of projects with developed controls on scope creep
  • D. Reduction in risk policy noncompliance findings
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
eblue
7 months ago
Selected Answer: C
C. Percentage of projects with developed controls on scope creep This KPI is directly related to the effectiveness of risk management practices within projects, as scope creep is a common risk in project management. By monitoring the percentage of projects that have developed controls to manage scope creep, the organization can gauge how well risk management practices are integrated into the PMO's processes. This is a more direct and specific measure compared to the other options, which are either too broad or not directly related to the risk management practices within projects.
upvoted 2 times
...
mynk29
11 months, 2 weeks ago
Selected Answer: D
It would be B if the there were senior management in place of steering co. Project never accepts risk.
upvoted 1 times
...
CbtL
1 year ago
Selected Answer: B
Agree with B.
upvoted 1 times
...
Broesweelies
1 year ago
Selected Answer: B
B. Percentage of projects with key risk accepted by the project steering committee Measuring the percentage of projects with key risks accepted by the project steering committee is the best key performance indicator (KPI) to determine how effectively risk management practices are embedded in the project management office (PMO). This KPI demonstrates that the PMO has identified and assessed risks, and the steering committee is actively involved in the decision-making process, providing a clear indication that risk management practices are integrated into the project lifecycle.
upvoted 2 times
...
ldl
1 year ago
Selected Answer: C
Ans should be C
upvoted 1 times
...
john_boogieman
1 year, 2 months ago
Selected Answer: B
Agree 'B'.
upvoted 2 times
...
Suchib
1 year, 3 months ago
Isnot it B
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.