During the implementation of an enterprise resource planning (ERP) system, an IS auditor is reviewing the results of user acceptance testing (UAT). The auditor's PRIMARY focus should be to determine if:
A.
application interfaces have been satisfactorily tested.
B.
all errors found in the testing process have been corrected.
C.
the business process owner has signed off on the results.
During the review of user acceptance testing (UAT) results, the IS auditor's primary focus should be to determine if the business process owner has signed off on the results. This ensures that the ERP system meets the business requirements and that the business process owner is satisfied with the performance of the system.
C. Reviewing the UAT doesn't ensure errors found in testing to be corrected. In the results auditor can determine if Business Owner has signed off or not.
The auditor's primary focus should be to determine if all errors found in the testing process have been corrected. It is important to ensure that all errors have been addressed and resolved before the system is implemented to avoid any potential issues or disruptions to business operations.
upvoted 3 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
SBD600
Highly Voted 1 year, 6 months agoPurpleParrot
Most Recent 1 month, 3 weeks agoblues_lee
9 months, 3 weeks agoBA27
1 year, 2 months agohoho
1 year, 4 months agonickchen
1 year, 10 months ago