Exam CRISC topic 1 question 19 discussion

Actual exam question from Isaca's CRISC
Question #: 19
Topic #: 1
[All CRISC Questions]

You are the project manager of GHT project. You have planned the risk response process and now you are about to implement various controls. What you should do before relying on any of the controls?

  • A. Review performance data
  • B. Discover risk exposure
  • C. Conduct pilot testing
  • D. Articulate risk
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
BKA
Highly Voted 4 years, 11 months ago
Q19 did not ask you to select 2 answers
upvoted 7 times
...
Anon530
Most Recent 1 month, 3 weeks ago
Answer is C. The question state "you have planned the risk response process and now you are about to implement various controls." Since you have not actually implemented the control, you do not have any data to evaluate the performance. The only other logical answer is to pilot test the control before implementation in production. Answer is C.
upvoted 4 times
...
mfourati
1 month, 3 weeks ago
Selected Answer: C
Before relying on any controls, it is important to conduct pilot testing to ensure that the controls are effective and can be implemented as planned. Pilot testing allows the project team to test the controls in a controlled environment, and to make any necessary adjustments before fully implementing them. This can help to prevent errors, delays, and additional costs that could be incurred if the controls were found to be ineffective or not feasible after implementation. A. Reviewing performance data refers to evaluating how well the controls are working, discovering risk exposure refers to identifying and analyzing new risks, and articulating risk refers to clearly and effectively communicating risks to stakeholders.
upvoted 1 times
...
SuperMax
1 month, 3 weeks ago
Selected Answer: C
C. Conduct pilot testing Pilot testing involves implementing the controls on a smaller scale or in a controlled environment to assess their effectiveness and identify any potential issues or unforeseen consequences. It allows you to test whether the selected controls can effectively mitigate the identified risks before fully implementing them across the entire project. Conducting pilot testing helps ensure that the controls are practical and that they will work as intended in the actual project environment. This step is crucial for risk management as it helps verify that the chosen controls are appropriate and do not introduce new risks or problems.
upvoted 2 times
...
ldl
1 year, 8 months ago
I would also go with C
upvoted 1 times
...
haitao1234
1 year, 8 months ago
Selected Answer: C
Pilot testing is important, reviewing performance data may not be able to tell whether the control is reliable or not
upvoted 1 times
...
Ndy
3 years ago
C is the correct answer
upvoted 1 times
...
TheSaintRaph
4 years ago
I will go with C, pilot testing is very important before you can rely on any controls, performance data review may not be able to provide that reliance
upvoted 2 times
...
simonsezzz
4 years, 10 months ago
so what is the final answer ,
upvoted 1 times
LMakoti
3 years ago
I would also go with C
upvoted 2 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...