For a large software development project, risk assessments are MOST effective when performed:

  • A. during the development of the business case
  • B. at each stage of the system development life cycle (SDLC)
  • C. at system development
  • D. before system development begins
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
CbtL
5 months, 2 weeks ago
Selected Answer: B
Agree with B.
upvoted 1 times
...
john_boogieman
8 months ago
'B' always.
upvoted 2 times
...
Jco
10 months, 3 weeks ago
#inexam 28/11
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.