Exam CRISC topic 1 question 207 discussion

Actual exam question from Isaca's CRISC
Question #: 207
Topic #: 1
[All CRISC Questions]

You are the project manager of project for a client. The client has promised your company a bonus, if the project is completed early. After studying the project work, you elect to crash the project in order to realize the early end date. This is an example of what type of risk response?

  • A. Negative risk response, because crashing will add risks.
  • B. Positive risk response, as crashing is an example of enhancing.
  • C. Positive risk response, as crashing is an example of exploiting.
  • D. Negative risk response, because crashing will add costs.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
kaykaymuon
1 month, 2 weeks ago
Selected Answer: C
Answer is C,
upvoted 1 times
...
Gachoki
1 year, 8 months ago
In this scenario, the project manager is not increasing the probability or impact of the opportunity itself. Instead, the project manager is taking actions to accelerate the project schedule and reduce the project duration, which is an example of exploiting the opportunity. While enhancing could potentially be used in other situations to increase the likelihood of completing a project early, in this specific scenario, crashing is a more appropriate example of exploiting. Answer is c
upvoted 1 times
...
ldl
1 year, 9 months ago
Selected Answer: C
answer is c
upvoted 1 times
...
helg420
1 year, 10 months ago
Selected Answer: C
agree the answer should be C. Ensuring it will happen is exploiting, not increasing the chances (enhancing).
upvoted 1 times
...
Bertolini
2 years, 1 month ago
The plausible correct is answer C. Exploiting is about doing everything to ensure that the event happens. In this risk response strategy, you make sure you realize the opportunity. Simply put, with the exploit risk response strategy, you increase the chance of the event happening to 100%. https://pmstudycircle.com/enhance-risk-response-vs-exploit-risk-response-strategies/
upvoted 2 times
...
Tingold1997
2 years, 3 months ago
The question states, "you elect to crash the project in order to realize the early end date". The likelihood wasn't increased, the positive response was realized as a direct result of your action which is the definition of exploiting risk. Please update.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago