A part of a project deals with the hardware work. As a project manager, you have decided to hire a company to deal with all hardware work on the project. Which type of risk response is this?
I would like to correct my answer. the answer should be A Transference for the following reason :
When the project manager hires a third party to handle the hardware work, it doesn’t transfer the overall project risk. Instead, it transfers the hardware-related risks (such as technical, operational, or compliance risks specific to hardware) to the third-party vendor.
Considering the first sentence in the question mentions "A part of a project deals with the hardware work." then the scope of transfered risk is hardware-related work.
Hiring a contractor does not transfer the risk to the contractor. The contractor is a project human resource and as an SME may be better able to complete the associated tasks. It may transfer the "accountability" in a RACI, but the PM is still going to be responsible. Transferring a risk generally refers to insurance.
i believe you are not transfering the risk but mitigating it by outsourcing to a provider but you still own the risk as HW is an asset of your project required to meet your business goals
This section is not available anymore. Please use the main Exam Page.CRISC Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
somkiatr
5 months agosomkiatr
5 months, 2 weeks agoRadko96
11 months, 2 weeks agoRUKidding
1 year agoChiubilly
1 year, 4 months agonikifor
2 years, 2 months agoSuchib
2 years, 4 months agoCarlos1406
2 years, 7 months agoMAUIIUAM
2 years, 4 months ago