An application owner has specified the acceptable downtime in the event of an incident to be much lower than the actual time required for the response team to recover the application. Which of the following should be the NEXT course of action?
A.
Invoke the disaster recovery plan (DRP) during an incident
B.
Reduce the recovery time by strengthening the response team
C.
Prepare a cost-benefit analysis of alternatives available
D.
Implement redundant infrastructure for the application
C. Prepare a cost-benefit analysis of alternatives available.
When there is a significant mismatch between the acceptable downtime specified by an application owner and the actual recovery time required, it's essential to prepare a cost-benefit analysis of available alternatives. This analysis will help in making an informed decision about the best course of action.
This section is not available anymore. Please use the main Exam Page.CRISC Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Staanlee
7 months, 4 weeks ago[Removed]
11 months, 3 weeks agoKoulyo
1 year agoCbtL
1 year agojohn_boogieman
1 year, 3 months agoaselunar
2 years, 11 months ago