Which of the following is the MOST important consideration for a risk practitioner when making a system implementation go-live recommendation?

  • A. Availability of in-house resources
  • B. Completeness of system documentation
  • C. Variances between planned and actual cost
  • D. Results of end-user acceptance testing
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
mraiyan
1 month, 1 week ago
Selected Answer: D
Agree UAT satisfaction is the most important consideration
upvoted 2 times
...
Ceecil1959
1 year, 3 months ago
I think documentation is correct because until it is complete and signed off, the system cannot be put into production.
upvoted 1 times
...
aselunar
2 years, 1 month ago
Should be D. See R3-142.
upvoted 1 times
...
[Removed]
2 years, 3 months ago
Agree, it should be UAT, which validates key functionality prior to Go-Live. Documentation can be updated later without affecting functionality.
upvoted 1 times
...
Khy
2 years, 3 months ago
The answer is not D?
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago