exam questions

Exam CRISC All Questions

View all questions & answers for the CRISC exam

Exam CRISC topic 1 question 186 discussion

Actual exam question from Isaca's CRISC
Question #: 186
Topic #: 1
[All CRISC Questions]

Beth is a project team member on the JHG Project. Beth has added extra features to the project and this has introduced new risks to the project work. The project manager of the JHG project elects to remove the features Beth has added. The process of removing the extra features to remove the risks is called what?

  • A. Detective control
  • B. Preventive control
  • C. Corrective control
  • D. Scope creep
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️
This is an example of a preventive control as the problem is not yet occurred, only it is detected and are accounted for. By removing the scope items from the project work, the project manager is aiming to remove the added risk events, hence it is a preventive control. Preventive control is a type of internal control that is used to avoid undesirable events, errors and other occurrences, which an organization has determined could have a negative material effect on a process or end product.
Incorrect Answers:
A: Detective controls simply detect and report on the occurrence of problems. They identify specific symptoms to potential problems.
C: Corrective actions are steps to bring the future performance of the project work in line with the project management plan. These controls make effort to reduce the impact of a threat from problems discovered by detective controls. They first identify the cause of the problems, then take corrective measures and modify the systems to minimize the future occurrences of the problem. Hence an incident should take place before corrective controls come in action.
D: Scope creep refers to small undocumented changes to the project scope.

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Kennethlim79
1 month, 2 weeks ago
The process of removing extra features that Beth added in order to reduce risks is an example of corrective control. Corrective control refers to taking steps to address issues, risks, or other problems that have already occurred in a project in order to get things back on track. By removing the extra features Beth added that introduced new risks, the project manager is implementing a corrective action to mitigate those risks. Preventive control refers to taking proactive measures to prevent potential issues or risks from occurring. Scope creep refers to uncontrolled changes in a project's scope. Detective control is not a standard project management term. So out of the options, corrective control best describes the process outlined in the scenario. The best answer is C. Corrective control.
upvoted 1 times
...
ldl
9 months, 2 weeks ago
Selected Answer: C
it should be corrective
upvoted 1 times
...
Prashil
2 years, 7 months ago
risk avoidance if it was an option.
upvoted 2 times
...
TheSaintRaph
3 years, 1 month ago
I would have thought the right answer is corrective, the question wasn't clear as to when the risks were discovered
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago