You have been assigned as the Project Manager for a new project that involves building of a new roadway between the city airport to a designated point within the city. However, you notice that the transportation permit issuing authority is taking longer than the planned time to issue the permit to begin construction. What would you classify this as?

  • A. Project Risk
  • B. Status Update
  • C. Risk Update
  • D. Project Issue
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️
This is a project issue. It is easy to confuse this as a project risk; however, a project risk is always in the future. In this case, the delay by the permitting agency has already happened; hence this is a project issue. The possible impact of this delay on the project cost, schedule, or performance can be classified as a project risk.
Incorrect Answers:
A: It is easy to confuse this as a project risk; however, a project risk is always in the future. In this case, the delay by the permitting agency has already happened; hence this is a project issue.
B, C: These are options are not valid.

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
reverse01
1 month, 1 week ago
D. Project Issue A project issue is an event or condition that has already happened and is negatively affecting the project's objectives. In this case, the delay in issuing the permit is an existing problem that is impacting the project's timeline.
upvoted 1 times
...
Rooks
3 years, 10 months ago
Not sure I understand or agree with this explanation. When a risk happened we take risk response actions e.g. mitigate, accept etc, and the scenario in this question fits the risk criteria, so why it can’t be classified as Project Risk?
upvoted 3 times
BTE
3 years, 7 months ago
In my opinion, the delay to the start (of this stage) of the project is an Issue because it has already occurred. However, the delay issue also poses follow-on risks of delays to future stages and completion of the project, and cost overruns.
upvoted 2 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago