David is the project manager of the HRC Project. He has identified a risk in the project, which could cause the delay in the project. David does not want this risk event to happen so he takes few actions to ensure that the risk event will not happen. These extra steps, however, cost the project an additional $10,000. What type of risk response has David adopted?
hammieo
Highly Voted 4 years, 11 months agokaykaymuon
Most Recent 5 months, 2 weeks agoRadko96
7 months, 3 weeks agoWills3rd
1 year agoJyLuv
1 year agoNdy
3 years, 2 months agoParth9
4 years, 4 months agoTTChizz
4 years, 6 months agouday1985
5 months, 2 weeks agoCL888
4 years, 5 months agotheApostle
5 years, 2 months agocatcklee
5 years, 6 months agoNdy
2 years, 1 month ago