David is the project manager of the HRC Project. He has identified a risk in the project, which could cause the delay in the project. David does not want this risk event to happen so he takes few actions to ensure that the risk event will not happen. These extra steps, however, cost the project an additional $10,000. What type of risk response has David adopted?
hammieo
Highly Voted 4 years, 7 months agokaykaymuon
Most Recent 4 weeks, 1 day agoRadko96
3 months agoWills3rd
7 months, 2 weeks agoJyLuv
7 months, 3 weeks agoNdy
2 years, 10 months agoParth9
4 years agoTTChizz
4 years, 2 months agouday1985
1 month agoCL888
4 years agotheApostle
4 years, 10 months agocatcklee
5 years, 1 month agoNdy
1 year, 9 months ago