Of the following, who is accountable for ensuring the representation of major stakeholders involved in a project?

  • A. Change control board
  • B. Steering committee
  • C. Project management office (PMO)
  • D. Project manager
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
46080f2
3 days, 21 hours ago
Selected Answer: B
The steering committee is responsible for ensuring the representation of major stakeholders in a project. This includes providing overall direction, ensuring alignment with business objectives, and involving representatives from all key areas impacted by the project. CISA Official Review Manual (Chapter 3, Figure 3.2: Project Management Roles and Responsibilities): "The steering committee provides overall direction and ensures appropriate representation of the major stakeholders in the project outcome." "It includes a senior representative from each business area that will be significantly impacted by the proposed new system or system modification."
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago