Question #: 1735
Topic #: 1
[All CISA Questions]

Which of the following is the GREATEST indication of scope creep in the management of a software development project?

  • A. Several change requests have been authorized by the project steering committee.
  • B. Some requirements are untraceable to the approved business case.
  • C. Project budget exceeds the allocated cost.
  • D. Project delivery has been delayed by several months.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
46080f2
3 days, 21 hours ago
Selected Answer: B
CISA Manual explicitly states, "Failure to adequately manage the requirements for a system through baselining can result in several types of risk. Foremost among these is scope creep—the process through which requirements change during development." This definition highlights that changes to requirements are the core of scope creep.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago