exam questions

Exam CRISC All Questions

View all questions & answers for the CRISC exam

Exam CRISC topic 1 question 283 discussion

Actual exam question from Isaca's CRISC
Question #: 283
Topic #: 1
[All CRISC Questions]

You have identified several risks in your project. You have opted for risk mitigation in order to respond to identified risk. Which of the following ensures that risk mitigation method that you have chosen is effective?

  • A. Reduction in the frequency of a threat
  • B. Minimization of inherent risk
  • C. Reduction in the impact of a threat
  • D. Minimization of residual risk
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️
The inherent risk of a process is a given and cannot be affected by risk reduction or risk mitigation efforts. Hence it should be reduced as far as possible.
Incorrect Answers:
A: Risk reduction efforts can focus on either avoiding the frequency of the risk or reducing the impact of a risk.
C: Risk reduction efforts can focus on either avoiding the frequency of the risk or reducing the impact of a risk.
D: The objective of risk reduction is to reduce the residual risk to levels below the enterprise's risk tolerance level.

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Joloms
1 month, 1 week ago
In the context of risk management, the effectiveness of a chosen risk mitigation method is ensured by its ability to reduce the impact or likelihood of the identified risk. The primary goal of risk mitigation is to lower the potential adverse effects that the risk may have on the project. Among the provided options, minimization of residual risk is the most comprehensive measure to determine the effectiveness of risk mitigation. Residual risk is the remaining risk after mitigation efforts have been applied. If the residual risk is minimized, it indicates that the risk mitigation methods have successfully reduced the overall risk to an acceptable level. Thus, the correct answer is: D. Minimization of residual risk
upvoted 1 times
...
Kennethlim79
7 months, 2 weeks ago
The correct answer is D. Minimization of residual risk. Residual risk is the risk that remains after risk mitigation measures have been implemented. It is the difference between the inherent risk (the risk before any mitigation measures are taken) and the mitigated risk. An effective risk mitigation method should minimize residual risk to an acceptable level. This means that the remaining risk should be low enough that it will not significantly impact the project's objectives. Reducing the frequency of a threat, minimizing inherent risk, and reducing the impact of a threat are all important steps in risk mitigation, but they are not sufficient to ensure that the method is effective. If the residual risk is still high, then the mitigation measures are not doing enough to protect the project from harm. Therefore, the most important factor in determining whether a risk mitigation method is effective is whether it minimizes residual risk to an acceptable level.
upvoted 1 times
...
SuperMax
9 months ago
Selected Answer: D
D. Minimization of residual risk When you opt for risk mitigation, you are primarily concerned with reducing the impact of a threat and minimizing the residual risk that remains after mitigation efforts. Residual risk is the risk that still exists after you have applied mitigation strategies. Therefore, ensuring that the risk mitigation method is effective means minimizing the residual risk to an acceptable level. Options A and C are related to the effectiveness of risk mitigation but do not cover the entire picture, as you should also consider the overall residual risk. Minimizing inherent risk (Option B) is generally done through other risk management activities, like risk identification and assessment, and may not be directly related to the effectiveness of a specific mitigation method.
upvoted 2 times
...
Julianleehk
1 year, 4 months ago
should be D
upvoted 2 times
...
Kozy
1 year, 9 months ago
The question asks how you can check if the chosen mitigation method is effective. This means that you managed to mitigate the inherent risk (inherent risk is the natural risk level without using controls or mitigations to reduce its impact or severity) resulting in some level of residual risk. Best if the residual risk is minimized therefore answer should be D.
upvoted 2 times
...
Prashil
3 years, 1 month ago
D should be the answer in my view
upvoted 1 times
...
Josh93
3 years, 2 months ago
should be D
upvoted 1 times
...
Shaws1
3 years, 4 months ago
Answer is D
upvoted 2 times
...
Tsuresh
3 years, 5 months ago
Should be D. Residual risk should be minimized
upvoted 2 times
...
Rooks
3 years, 10 months ago
I agree that the explanation is poor and wrong but the answer is right. The Mitigation mostly is about reducing the inherent risk to an acceptable level. Answer C is referring to Threat...
upvoted 2 times
...
Abhaythemagician
4 years ago
I agree. If risks are identified by a particular architecture, you can change the architecture so the inherent risk is reduced. SO changing the architecture is a way of mitigation.
upvoted 1 times
...
Stanislav_crisc
4 years ago
reduced risk - amount of risk after applied controls, but you can reduce inherent risk by change design for example, so no additional cotrol (and costs to support) needed. so best idea is to reduce inherent risk
upvoted 1 times
...
YWLow
4 years, 4 months ago
This is a wrong answer. The explanation conflicts with the questions.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago