Which of the following is the BEST recommendation to drive accountability for achieving the desired outcomes specified in a benefits realization plan for an IT project?
A.
Document the dependencies between the project and other projects within the same program.
B.
Ensure that IT takes ownership for the delivery and tracking of all aspects of the benefits realization plan
C.
Ensure that the project manager has formal authority for managing the benefits realization plan.
D.
Assign responsibilities, measures, and timelines for each identified benefit within the plan.
Justification after reading the Manual 28th ed:
Accountability via Defined Roles:
The CISA Review Manual emphasizes that "key elements of project benefits realization" include "assigning a measure and target," "establishing a tracking/measuring regimen," and "establishing key responsibilities for realization"1. Explicitly assigning responsibilities ensures clear ownership for each benefit.
Alignment with Phases of Benefits Realization:
Figure 3.4 in the manual outlines four phases of benefits realization, including "assigning a measure and target" and "documenting the assumption"1. This highlights the necessity of defining measurable outcomes with timelines to track progress.
upvoted 1 times
...
This section is not available anymore. Please use the main Exam Page.CISA Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.