When reviewing the acquisition for a new application, which of the following is MOST important to ensure was included in the request for proposal (RFP) process?
Hayati, you are killing me, you voting and saying "Why not (answer)" adds zero value to the conversation. Regardless in this case I agree it is A. The reason being if there is not user acceptance testing then you can not ensure or validate that it meets the user requirements and needs. The RFP should include user acceptance testing.
System development methodology
Including the system development methodology in the RFP process is essential because it helps evaluate the vendor's approach to developing and delivering the application. Understanding the methodology ensures that the project aligns with the organization’s expectations for quality, timelines, and collaboration. It also helps determine whether the vendor's processes are compatible with the organization’s needs, such as agile, waterfall, or other methods.
A. User acceptance testing (UAT) plan can be important but is generally more relevant in later stages of the project, not at the RFP stage.
B. Vendor financial stability is often evaluated through due diligence after selecting a vendor but may not be explicitly detailed in the RFP.
C. Vendor KPIs are useful for performance monitoring post-implementation but are less relevant at the RFP stage.
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
blehbleh
1Â month agoVima234
2Â months, 1Â week agoHayati
2Â months, 3Â weeks ago