Question #: 1707
Topic #: 1
[All CISA Questions]

Which of the following should be of GREATEST concern to an IS auditor assessing an organization's patch management program?

  • A. Patches for medium- and low-risk vulnerabilities are omitted.
  • B. Patches are deployed from multiple deployment servers.
  • C. There is no process in place to quarantine servers that have not been patched.
  • D. There is no process in place to scan the network to identify missing patches.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
blehbleh
1 month ago
Selected Answer: D
I have to go with D. If you aren't even scanning your network to find vulnerabilities how would you know what to quarantine or what patches to release on which systems or servers. D makes the most sense as it is the starting point to patch management.
upvoted 1 times
...
PurpleParrot
3 months, 1 week ago
Selected Answer: C
Not having a quarantine process is the biggest risk
upvoted 1 times
PurpleParrot
1 month, 1 week ago
I change my answer D.
upvoted 1 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...