Shortly after a system was deployed into production, it was identified that some key scenarios were not tested during user acceptance testing (UAT). Which of the following is the GREATEST concern with this situation?
A.
The system may have gone into production with defects.
B.
System functions may not meet business requirements.
C.
Significant security risks may not have been assessed.
D.
Extra funding may be required to complete the testing.
Let me expand a little. In reading the question it specifically states UAT. Therefore, if proper UAT did not take place then it will not meet the system functions. We are concerned with the functionality because of poor UAT. Not security.
It is B.
A. Defects: While defects are a concern, UAT primarily focuses on ensuring the system fulfills its intended purpose according to user needs. Unforeseen defects might still exist, but untested functionalities related to business requirements are a bigger risk.
The core purpose of UAT is to validate if the system fulfills the needs of the users and aligns with the business goals. Untested key scenarios raise the biggest concern that the system might not be meeting those expectations.
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
blehbleh
4 weeks agoblehbleh
4 weeks agoRS66
3 months agoBinagr8
3 months, 4 weeks agojoehong
3 months, 4 weeks agoRS66
3 months ago