Question #: 1277
Topic #: 1
[All CISA Questions]

An IS auditor is performing a project review and finds that scope reductions have been made without proper authorization. The IS auditor should be MOST concerned that:

  • A. there could be significant delays in project completion.
  • B. the project has not followed project management standards.
  • C. project costs could increase above the original project budget.
  • D. anticipated business functionality may not be delivered.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
RS66
3 months, 2 weeks ago
Selected Answer: D
D. anticipated business functionality may not be delivered.
upvoted 2 times
...
Swallows
4 months, 1 week ago
Selected Answer: B
This is the most concerning issue because unauthorized scope reductions indicate a failure to adhere to established project management processes, which can lead to further governance and accountability issues in the project.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...