An IS auditor is performing a project review and finds that scope reductions have been made without proper authorization. The IS auditor should be MOST concerned that:
A.
there could be significant delays in project completion.
B.
the project has not followed project management standards.
C.
project costs could increase above the original project budget.
D.
anticipated business functionality may not be delivered.
This is the most concerning issue because unauthorized scope reductions indicate a failure to adhere to established project management processes, which can lead to further governance and accountability issues in the project.
upvoted 1 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
RS66
3 months, 2 weeks agoSwallows
4 months, 1 week ago