For which of the following risk management capability maturity levels do the statement given below is true? "Real-time monitoring of risk events and control exceptions exists, as does automation of policy management"
Suggested Answer:C🗳️
An enterprise's risk management capability maturity level is 5 when real-time monitoring of risk events and control exceptions exists, as does automation of policy management. Incorrect Answers: A, D: In these levels real-time monitoring of risk events is not done. B: In level 0 of risk management capability maturity model, enterprise does not recognize the importance of considering the risk management or the business impact from IT risk.
It's correct. Level 5. because is optimitzed with automation
C. Level 5
The statement "Real-time monitoring of risk events and control exceptions exists, as does automation of policy management" aligns with the risk management capability maturity level 5. At this level, organizations have achieved a high level of maturity in their risk management practices.
Level 5 represents an optimized level of risk management capability, where organizations have established a proactive and continuous risk monitoring and control framework. Real-time monitoring of risk events and control exceptions means that organizations are actively monitoring and detecting risks as they occur, allowing for immediate response and mitigation.
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Radko96
3 months, 2 weeks agodedfef
8 months, 1 week agoRadko96
3 months, 2 weeks ago