What is the BEST method to determine if IT resource spending is aligned with planned project spending?

  • A. Return on investment (ROI) analysts
  • B. Critical path analysis
  • C. Earned value analysis (EVA)
  • D. Gantt chart
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
3008
1 month, 2 weeks ago
EVA is a project management technique that provides an objective measurement of a project's performance in terms of cost and schedule. It integrates the project scope, schedule, and cost elements to determine how well a project is progressing. EVA enables organizations to determine if IT resource spending is aligned with planned project spending by comparing the actual cost and schedule performance against the planned cost and schedule performance.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago