When creating an incident response plan, the triggers for the business continuity plan (BCP) MUST be based on:

  • A. a threat assessment.
  • B. recovery time objectives (RTOs).
  • C. a business impact analysis (BIA).
  • D. a risk assessment.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Soleandheel
1 month, 2 weeks ago
C. a business impact analysis (BIA).
upvoted 1 times
...
richck102
1 month, 3 weeks ago
D also make sense. .....but i pick C
upvoted 2 times
Soleandheel
1 month, 2 weeks ago
Exactly!
upvoted 1 times
...
...
richck102
1 month, 3 weeks ago
Selected Answer: C
C. a business impact analysis (BIA).
upvoted 4 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago