Which of the following provides the BEST evidence of effective IT portfolio management?

  • A. Programs in the IT portfolio are prioritized by each business function.
  • B. The IT portfolio is updated on the basis of current industry benchmarks.
  • C. The IT portfolio is updated as business strategy changes.
  • D. IT portfolio updates are communicated when approved.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
FAGFUR
4 months ago
Selected Answer: C
The best evidence of effective IT portfolio management is when the IT portfolio is updated as business strategy changes. IT portfolio management involves aligning IT investments with business objectives, and regular updates to the portfolio based on changes in business strategy demonstrate responsiveness to the evolving needs and goals of the organization. The most compelling evidence of effective IT portfolio management is the proactive adjustment of the portfolio in response to changes in the broader business strategy.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago